How Long Does It Take to Build a Deck?

Building a deck takes a contractor 1 to 3 days for a small deck, 3 to 7 days for a medium one and 1 to 3 weeks for a large deck. The design and the permit before it often take longer than the build.

Book early: spring and summer are every deck builder’s busy season.

The seven stages, in order

This is one real backyard, photographed at every stage from the same spot. The times are typical ranges for each stage; your builder’s schedule is the one that counts.

  1. The deck drawn up in pencil against the back of the house: the frame, the wide stairs and the railings

    Stage 1 of 7

    Design and permit

    Often a few weeks

    Size, height, stairs, railings and boards get chosen and drawn, and the permit goes in if your city needs one. A raised deck almost always does.

  2. The backyard with the old deck torn out, the layout strung and every pile spot marked in orange

    Stage 2 of 7

    Tear-out and layout

    About a day

    Any old deck comes out, utilities are located, and the layout is strung with every footing or pile spot marked.

  3. The same yard with the black steel screw piles in and cut level

    Stage 3 of 7

    Footings or screw piles

    1 to 2 days, then inspection

    Steel screw piles go in and get cut level in a day; poured footings need time to cure. Many cities inspect footings before anything is built on them.

  4. The same yard with the new deck framed on the piles, joists and blocking in

    Stage 4 of 7

    Framing

    1 to 3 days

    Beams, joists, ledger and blocking go on. A level, square frame is what makes the boards and railings go on clean.

  5. The same deck with the grey composite boards and fascia on, no railings or stairs yet

    Stage 5 of 7

    Decking boards

    2 to 5 days

    Boards and fascia go on. Composite and picture-frame borders take longer than plain pressure-treated boards.

  6. The same deck with the black aluminum railings and the wide stairs on, the skirting still to go

    Stage 6 of 7

    Stairs and railings

    1 to 3 days

    Stairs get built and railings go on. Aluminum and glass railings are often ordered to size, so ask early when they arrive.

  7. The deck finished: composite boards, black aluminum railings, wide stairs to the lawn and the post-cap lights on

    Stage 7 of 7

    Skirting, lights and final inspection

    1 to 2 days

    Skirting, lights and the last trim go on, the final inspection is booked, and you walk the deck together.

What decides how long yours takes

  • The permit. Often the longest wait. Your city decides whether you need one and how long it takes.
  • Size and height. A raised or multi-level deck means more footings, more framing and more inspections.
  • Materials. Composite boards and made-to-size railings take longer to install and sometimes to arrive.
  • Season. Spring and summer book up early; a fall build often starts sooner.
  • Weather and ground. Rain, frozen ground and rock where a footing goes all push the schedule.

Getting ready for the build

A few things make the build days go smoothly:

  • Have utilities located before anyone digs: your builder can book it
  • Clear a path through the side yard for materials and keep pets inside
  • Check whether your homeowners association needs to approve the design

Knowing where yours is at

A live deck timeline on a phone: framing today, stage 4 of 8, on track

Even a short build has days where nothing seems to happen, like waiting on an inspection or a railing order. More builders now send a live timeline instead: one link that shows the stage you are in, today’s photos and the next step.

The Novaks’ deck on their phone, mid-build: framing today, stage 4 of 8.

See the Novaks’ full timeline →

If your builder doesn’t send one, show them this page.

Questions homeowners ask

How long does it take to build a small deck?

A contractor can build a small deck, up to about 200 sq ft, in 1 to 3 days once the permit and materials are in.

Do I need a permit to build a deck?

Usually yes for a raised deck or one attached to the house, and sometimes not for a low, freestanding one. Your city decides.

How long does it take to build a composite deck?

Longer than pressure-treated wood: composite boards need more precise spacing and hidden fasteners, and picture-frame borders add time.

Are screw piles faster than concrete footings?

Yes. Screw piles go in and can carry the frame the same day, while concrete footings need time to cure first.

When is the best time to build a deck?

Book in winter for a spring build, or build in the fall when builders are less busy. Frozen ground makes footings harder in deep winter.

Sources: build times by deck size from Advantage Lumber, “How Long Does it Take to Build a Deck?” (July 2023). Stage times are typical ranges reported by deck builders.