Kyle BrandtYour contractor
Backyard Deck Build · for the Novak Family
Today · stage 4 of 8On track

Framing & Inspection

48%of the job done
Nov 12Finish · 2026
DesignOct 9
Tear-outOct 17
PilesOct 20
FramingToday
DeckingOct 31
RailingsNov 4
SkirtingNov 8
WalkthroughNov 11
Framed and ready for inspection
48% doneFinish Nov 12
Oct 28 · Framing
Kyle Brandt · 50 min ago

The frame is done: beams are on the piles, every joist is in and the blocking is set. Framing inspection is booked for tomorrow morning, and once it passes we start laying your boards.

Next up DeckingOct 31

The whole job

Started Sep 24Finish Nov 12, 2026Budget $19.8k of $42k
  1. Oct 9

    Design & Permit

    Done

    Deck layout, materials and railings, drawings and the building permit.

    Kyle Brandt · Oct 9

    Permit is approved! The drawings have the deck across the back of the house, freestanding on screw piles, with composite boards, black aluminum railings and wide stairs down to the lawn.

  2. Oct 17

    Tear-Out & Layout

    Took 2 days

    Tear out the old deck, string the layout and mark every pile.

    Kyle Brandt · 11 days ago

    The old deck is torn out and stacked for the bin. The layout is strung and every pile spot is marked in orange for the pile crew.

  3. Oct 20

    Screw Piles

    Took 1 day

    Screw piles driven below the frost line, cut level and capped with brackets.

    Kyle Brandt · 8 days ago

    Piles are in! Every one hit its torque below the frost line, and they are all cut level with the brackets on. Framing starts next.

  4. Today

    Framing & Inspection

    Ready Oct 30

    Beams on the piles, joists and blocking, then the framing inspection.

    Kyle Brandt · 50 min ago

    The frame is done: beams are on the piles, every joist is in and the blocking is set. Framing inspection is booked for tomorrow morning, and once it passes we start laying your boards.

    Questions on this stage 5

    • You · 3 hours agoIt is so much bigger than the old one! Are the stairs still coming straight down the middle to the lawn?
    • Kyle · 2 hours agoYes, centred on the frame, same as the drawings. Five feet wide, so two people can pass on them.
    • You · 2 hours agoPerfect. Could we add a plug on one of the railing posts for a heater next summer?
    • Kyle · 1 hour agoEasy, the frame is still open so the electrician can run it before the boards go down. I’ll send you a quick quote today. No change to the schedule.
    • You · 35 min agoAmazing, thank you!
  5. Nov 4

    Railings & Stairs

    About 3 days

    Black aluminum railings and the wide stairs down to the lawn.

  6. Nov 8

    Skirting & Lighting

    About 2 days

    Slatted composite skirting and the post-cap lights.

  7. Nov 11

    Final Inspection & Walkthrough

    Wraps Nov 12

    Final inspection, clean-up and a walkthrough with you.

Last updated 45 min agoLive timeline on TR△CE
Backyard Deck Build · live timeline