Cole BennettYour contractor
Backyard Pool Build · for the Reyes Family
Today · stage 4 of 9On track

Gunite Shell

46%of the job done
Nov 18Finish · 2026
DesignOct 7
DigOct 11
SteelOct 21
GuniteToday
TileNov 2
DeckNov 7
PlasterNov 12
StartupNov 14
WalkthroughNov 17
Shell sprayed, curing
46% doneFinish Nov 18
Oct 30 · Gunite
Cole Bennett · 50 min ago

The shell and the steps are sprayed and looking great. We’re watering it twice a day while it cures, so it comes out strong. Tile and coping start next week.

Next up TileNov 2

The whole job

Started Sep 10Finish Nov 18, 2026Budget $39.5k of $86k
  1. Oct 7

    Design & Permits

    Done

    Pool design, tile and coping picks, permit and utility locates.

    Cole Bennett · Oct 7

    The permit is approved and the locates are clear! The plan has the 16 by 32 pool with wide steps at the house end, blue glass waterline tile, travertine coping and a broom-finish deck all round.

  2. Oct 11

    Excavation

    Took 2 days

    Lay out the pool, dig it to depth and haul the dirt.

    Cole Bennett · Oct 11

    The pool is dug to depth and the dirt is hauled away. The inspector checks the layout tomorrow, then the steel goes in.

  3. Oct 21

    Steel & Plumbing

    Took 6 days

    Tie the rebar cage, run the plumbing and the light conduit, inspection.

    Cole Bennett · 9 days ago

    The steel is tied, the plumbing and the light conduit are in, and the inspection passed this morning. Gunite is booked for Monday.

  4. Today

    Gunite Shell

    Ready Nov 1

    Spray the concrete shell and steps, then keep it wet for a week while it cures.

    Cole Bennett · 50 min ago

    The shell and the steps are sprayed and looking great. We’re watering it twice a day while it cures, so it comes out strong. Tile and coping start next week.

    Questions on this stage 5

    • You · 3 hours agoIt looks so much bigger now! Do we need to water it too?
    • Cole · 2 hours agoNo, we’ve got it. Our crew wets it down morning and evening all week, so you don’t need to do a thing.
    • You · 2 hours agoGreat. Is it too late to look at a different waterline tile?
    • Cole · 1 hour agoNot at all, tile goes on next week, so you have until Friday. I’ll drop off three samples tomorrow. No change to the schedule.
    • You · 35 min agoPerfect, thank you!
  5. Nov 7

    Decking

    About 3 days

    Form, steel and pour the broom-finish concrete deck.

  6. Nov 12

    Plaster & Fill

    About 2 days

    White plaster finish, then fill the pool.

  7. Nov 14

    Startup

    About 3 days

    Start the equipment, balance the water and set the lights on a timer.

  8. Nov 17

    Final Walkthrough

    Wraps Nov 18

    Clean-up and pool school: the equipment, the chemistry and the app, with you.