Shingles are on, every window is in and the house is wrapped. We are locked up before the rain. Plumbers start rough-in Monday.
Plans, engineering, lot grading and the building permit.
Building permit is approved! The stamped plans have the board-and-batten front, the stone porch and the bonus room over the garage.
Dig, footings, foundation walls and damp-proofing, then inspection.
Foundation is poured and the forms are off. Footings and walls passed inspection and the damp-proofing is on.
Floors, walls, stairs and roof trusses, then framing inspection.
Framing passed inspection! The roof is decked, the stairs are in and you can walk the bonus room now.
Shingles, windows, house wrap and doors, so the house is closed in.
Shingles are on, every window is in and the house is wrapped. We are locked up before the rain. Plumbers start rough-in Monday.
Plumbing, electrical and heating rough-in, inspection, then insulation.
Board-and-batten, stacked stone at the porch, soffits and trim.
Drywall, cabinets, floors, tile, trim and paint.
Pour the driveway, front walk and porch steps.
Final grade, sod, trees and shrubs.
Occupancy inspection, clean, walkthrough and your keys.