Ryan MercerYour contractor
Custom Home Build · for the Walsh Family
Today · stage 4 of 10On track

Roof, Windows & Lock-Up

36%of the job done
Jun 3Finish · 2027
DesignJul 2
FoundationJul 28
FramingSep 6
Lock-upToday
Rough-insNov 4
SidingNov 21
InteriorDec 7
DrivewayMay 2
LandscapingMay 12
KeysMay 28
Wrapped, windows in, locked up
36% doneFinish Jun 3
Oct 28 · Lock-up
Ryan Mercer · 50 min ago

Shingles are on, every window is in and the house is wrapped. We are locked up before the rain. Plumbers start rough-in Monday.

Next up Rough-insNov 4

The whole job

Started May 31Finish Jun 3, 2027Budget $344k of $840k
  1. Jul 2

    Design & Permits

    Done

    Plans, engineering, lot grading and the building permit.

    Ryan Mercer · Jul 2

    Building permit is approved! The stamped plans have the board-and-batten front, the stone porch and the bonus room over the garage.

  2. Jul 28

    Excavation & Foundation

    Took 20 days

    Dig, footings, foundation walls and damp-proofing, then inspection.

    Ryan Mercer · Jul 28

    Foundation is poured and the forms are off. Footings and walls passed inspection and the damp-proofing is on.

  3. Sep 6

    Framing

    Took 5 weeks

    Floors, walls, stairs and roof trusses, then framing inspection.

    Ryan Mercer · Sep 6

    Framing passed inspection! The roof is decked, the stairs are in and you can walk the bonus room now.

  4. Today

    Roof, Windows & Lock-Up

    Ready Nov 3

    Shingles, windows, house wrap and doors, so the house is closed in.

    Ryan Mercer · 50 min ago

    Shingles are on, every window is in and the house is wrapped. We are locked up before the rain. Plumbers start rough-in Monday.

    Questions on this stage 5

    • You · 4 hours agoIt finally looks like a house with the windows in! Is the big window in the bonus room the size we picked?
    • Ryan · 3 hours agoYes, the 6-foot slider you picked, same as on the plans. You can see the view from up there now.
    • You · 2 hours agoLove it. While the walls are open, could we add a plug on the porch for Christmas lights?
    • Ryan · 1 hour agoEasy, the electrician starts rough-in Monday. I’ll add it to his list and send you a quick quote today. No change to the schedule.
    • You · 40 min agoPerfect, thank you!
  5. Nov 21

    Siding & Stone

    About 3 weeks

    Board-and-batten, stacked stone at the porch, soffits and trim.

  6. Dec 7

    Drywall & Interior Finishing

    About 20 weeks

    Drywall, cabinets, floors, tile, trim and paint.

  7. May 2

    Driveway & Walks

    About 1 week

    Pour the driveway, front walk and porch steps.

  8. May 12

    Landscaping

    About 2 weeks

    Final grade, sod, trees and shrubs.

  9. May 28

    Final Inspection & Possession

    Wraps Jun 3

    Occupancy inspection, clean, walkthrough and your keys.

Last updated 45 min agoLive timeline on TR△CE
Custom Home Build · live timeline