Jordan ReyesYour contractor
Basement Development · for the Patel Family
Today · stage 4 of 10On track

Drywall & Taping

48%of the job done
Dec 5Finish · 2026
DesignSep 28
LayoutOct 1
FramingOct 16
DrywallToday
PaintNov 2
FlooringNov 7
BathroomNov 11
Built-insNov 19
LightsNov 26
WalkthroughDec 1
Board up, first coat of mud
48% doneFinish Dec 5
Oct 28 · Drywall
Jordan Reyes · 50 min ago

Board is up and the first coat of mud is on. Ceiling holes are cut for the pot lights. Sanding Thursday, then paint.

Next up PaintNov 2

The whole job

Started Sep 16Finish Dec 5, 2026Budget $31.5k of $68k
  1. Sep 28

    Design & Permits

    Done

    Layout, media wall and bathroom plan, development permit.

    Jordan Reyes · Sep 28

    Permit is approved. Media wall, the bathroom off the family room and the egress window are all on the stamped drawings.

  2. Oct 1

    Clean-Out & Layout

    Took 2 days

    Clear the space, snap the wall lines, check the slab and drains.

    Jordan Reyes · Oct 1

    Space is cleared and every wall is snapped on the slab. Floor drain and slab both check out.

  3. Oct 16

    Framing & Rough-In

    Took 14 days

    Frame the walls, run wiring, plumbing and ductwork, then inspection.

    Jordan Reyes · 12 days ago

    Framing and rough-in passed inspection this morning. Insulation and vapour barrier are in, so drywall starts Monday.

  4. Today

    Drywall & Taping

    Ready Nov 1

    Board, tape and mud the walls and ceiling.

    Jordan Reyes · 50 min ago

    Board is up and the first coat of mud is on. Ceiling holes are cut for the pot lights. Sanding Thursday, then paint.

    Questions on this stage 5

    • You · 3 hours agoThe ceiling looks so much higher with the board up! Are the pot lights staying where we marked them?
    • Jordan · 2 hours agoYes, exactly where you marked them: six in the family room, one over the bathroom door. The holes are cut, so you can see the spacing now.
    • You · 2 hours agoPerfect. Could we add an outlet behind the TV for a soundbar while the walls are open?
    • Jordan · 1 hour agoEasy, the box is already there for the TV. I’ll add a second one beside it and send a quick quote today. No change to the schedule.
    • You · 35 min agoAmazing, thank you!
  5. Nov 7

    Flooring

    About 3 days

    Underlay and luxury vinyl plank through the family room.

  6. Nov 11

    Bathroom Tile & Fixtures

    About 7 days

    Shower tile, vanity, toilet and fan.

  7. Nov 19

    Media Wall & Trim

    About 6 days

    Built-in media wall, doors, casing and baseboards.

  8. Nov 26

    Lights & Final Electrical

    About 3 days

    Pot lights, switches, outlets and final electrical inspection.

  9. Dec 1

    Final Inspection & Walkthrough

    Wraps Dec 5

    Final inspection, clean and walkthrough with you.

Last updated 45 min agoLive timeline on TR△CE